Work on the overhaul of 5025 began at the beginning of 2012. This was thanks to grants or promises of support from the Strathspey Railway Company, the Strathspey Railway Trust, the Heritage Lottery Fund the Strathspey Railway Association and the significant amount which had already been raised from our supporters though appeals.

Major progress has been made on the locomotive and tender frames, axleboxes, motion, dragboxes and valve gear at Aviemore and on the major rebuild of the boiler, reprofiling of the tyres of the locomotive and tender wheels and construction of a new tender tank at Riley Engineering of Bury. Work has also included the casting and machining of a pair of new cylinders

The WEC Watkinson Trust originally hoped to return 5025 to service in 2015, however owing to the amount of work needed, we now hope that the engine will be ready towards the end of the 2019 season. ( see edit below)

We are still on track for 2019 to be the year in which the oldest and best example of a L.M.S. Black Five steams again. Due to a very tight budget the original intention was to return 5025 to traffic by carrying out the minimum necessary work. However, she is an iconic locomotive and quite early on the sensible decision was taken to restore her to “as new” condition. This has resulted in considerable extra work and expense and has left the Watkinson Trust desperate for funds.

Edit, we were heavily delayed waiting for the boiler, this has put the completion date back to around summer 2020.

Further edit, owing to covid lockdown, this has been further delayed, completion date is now summer 2021.

The original budget of £354,050 has been spent wisely and with care. However, additional boiler work has cost a further £39,345, new cylinders and frame repairs £33,350, and other work such as a new cab, injectors and super heaters upwards of £22,500.

Although most of the work now being carried out is labour intensive, certain costly goods and services are essential to finishing the job and it is only with your help that we can make it happen.

We still need to complete the tender tank and the under frame, produce boiler cladding, purchase copper pipe and various fixings and fastenings and pay for transport, crane hire and specialist machining.

The Watkinson Trust would like to thank you for any generous donation you are able to make towards a successful conclusion.

Please use the “Donate” facility below to support this worthwhile project through Paypal.














Sunday 22 November 2015

22nd November 2015

Its been a while since the last post, I haven't forgotten but there really isn't much to report at the moment.  Other work is taking priority such as the maintenance on our other engines in preparation for the Christmas running.

This is a flitch plate repair to part of the running plate, now awaiting welding.


More work on the running plate, this time at the cab end.


Two driving axles have had their axle boxes fully fitted for the final time, these have been covered with plastic to protect them up to the time that they can be fitted.


Another view.


These are the old horn guide clips, slightly worse for wear.


New stronger horn guide clips are being fabricated.


Nathan machining a part.


A collection of pins that have been machined for the loco.


More horn guide clip fabrication.


This piece goes across the end of and supports the cab floor, so i'm told.


Apart from the other engines, the steam generator on the class 27 is also taking people away from the black 5.  This is part of it that is undergoing patch repairs.


The steam generator exhaust, a complete replacement being made.