About the Trust


Work on the overhaul of 5025 began at the beginning of 2012. This was thanks to grants or promises of support from the Strathspey Railway Company, the Strathspey Railway Trust, the Heritage Lottery Fund the Strathspey Railway Association and the significant amount which had already been raised from our supporters though appeals.

Major progress has been made on the locomotive and tender frames, axleboxes, motion, dragboxes and valve gear at Aviemore and on the major rebuild of the boiler, reprofiling of the tyres of the locomotive and tender wheels and construction of a new tender tank at Riley Engineering of Bury. Work has also included the casting and machining of a pair of new cylinders

The WEC Watkinson Trust originally hoped to return 5025 to service in 2015, however owing to the amount of work needed, a more realistic aim is for completion is towards the middle / end of 2017.

To achieve this further donations to the WEC Watkinson Trust will be welcomed by our treasurer: WAD Macphail CA, ‘Ardneil’, 80 Bruceland Road, Elgin, Moray, IV30 1SP.





Thursday, 16 October 2014

Latest news 16.10.2014

The front end continues to be built up, the intention is to get all components in place prior to riveting them all up in one go.
Here the new cross channels have been fitted behind the support brackets.
 





 Another view taken from further back


The old corroded cross member.


Nathan and Tommy with the new cross member, prior to fitting it in position.


The cross member now in place ready for hole drilling.


STOP PRESS

Both cylinders have now been cast and delivered to the engineers for machining.